Wednesday, 2 July 2008

The Position in Mid-June


After our efforts to get the preparations completed for the flooring we now have a concrete ground floor in the majority of the eastern end of the house and this would have dried out much more rapidly had it not been for the appalling weather we have experienced – it has rained at some point in each 24 hours for the past month and we have had some amazing storms where the amount of water coming down has overwhelmed the new guttering and it’s simply poured down the side of the house.

Jean Claude has also constructed a first floor in new wood in the centre part of the house, and most of the wall needed to form the bedroom in that part of the house has been put up. So in the centre of the house there is a clearly defined hallway, a downstairs operational loo, a cupboard with the board for the mains electricity supply and a ‘developing’ bedroom with en suite bathroom. These though still need a good deal of work for them to be in any sense complete and useable by us.

Importantly the electrician is due to come back to the house in the next few days and wire up the majority of the eastern end giving us sockets and lighting. There will also be an electric hot water tank to service the western end of the house – there will have to be a separate tank for the eastern end as the house is so big. The problem with all of this is that the electrician and the builder do not exactly get on with each other and I am something of a ‘piggy-in-the-middle’ trying to ensure that they do actually collaborate and produce what we want.

A very late April Posting - Less, but More


We returned as planned in early April bringing two cars, loads of stuff to keep us going for the next six months and our dog. We had dreaded the journey for ages as Morag, the dog, had proved herself to be a very bad traveller. But in Joanne’s car she proved to be perfectly O.K. and indeed a good companion on the very long journey – we did the drive in one day, a foolish thing to do but it got the journey out of the way swiftly.

From the progress report we had had from our builder we had hoped that there would have been a completed floor in the centre of the house with the construction of a wall allowing for the installation of a bathroom. However, when we met him it emerged that he had injured himself falling out of a tree that he was lopping and had been unable to work for three and a half weeks. So no real progress had been made from the installation of the septic tank and the six windows.

But our presence here has re-energised the project and much progress has subsequently been made, albeit as a consequence of the efforts that we have made. The floor in what will be the central hallway area has been fully dug out and hardcore pebbles put in. In the large room we have cleared away all the rubbish and again shifted pebbles into it – this is not yet complete and we have another delivery of 10 tonnes of pebbles to face moving. A telephone connexion has also finally been made – there was a problem with a blockage in the pipe under the road which took a deal of solving. We now have a landline connexion but it cannot support broadband unfortunately, so it’s dial-up only for us.

The water supply has also been brought through into the house with a new connexion to the meter. Again though there was a problem in that there was a leak on the water company’s side of the meter so they had to come out and fix that. After considerable effort by the technician sent out to deal with it, and a new meter, we were re-connected. And on Sunday we shall have electricity inside the house to provide sockets for the fridge, freezer and washing machine we have also acquired. So as Jean Claude keeps saying as we make progress – toute moderne!

Notwithstanding the humour we are beginning to be really hopeful that we can effectively move into the house in summer with a full range of facilities available to us.

Tuesday, 1 April 2008

And now a Fosse Septique!



As noted in the last posting the contractor putting in the septic tank was due to start in mid-March and indeed it can now be seen that he actually did do so. Another e-mail from Jean-Claude with pictures shows further progress demonstrated above. It appears that the work on the fosse is finished, including the filter bed in our field, together with the pipe-work under the road. Connexions still have to be completed but it does seem that it will be possible to install a bathroom pretty soon which will make staying in the house a pleasanter prospect.

The other thing to note in the pictures is that six windows have also been installed at the front. Together with the completed roof this means that the house is rapidly becoming weatherproof which will encourage the drying-out process.

Much to look forward to on a return to the house then!

Sunday, 16 March 2008

We Are Weatherproof





The confidence expressed in the last posting has been met, sort of! We have just returned from a short visit to Arné and as the pictures above demonstrate we now have a complete roof over the whole of the house so it is now weatherproof and the inside can really dry out. But as you can see from the picture of the back there is no window in the roof; neither a dormer, which is what the plans demand, nor a velux, which is what Jean Claude says we can get away with. It is also the case that the internal structure holding the roof up at the north eastern end has not been altered radically. Which means that we have a real problem with the levels inside the house, and if it stayed that way we could not put in the rooms that we plan. We spent a very worried 24 hours contemplating all this until I managed to talk it through with Jean Claude. He was quite insouciant – yes he knew that there were things that need to be done and he would do them in this way, etc. So no problems at all and we could stop our worrying.

With the roof in this state we can move to deal with the inside now and we have started to demolish the wall to create the large room at the south western end of the house. Not as easy as it sounds as concrete has been used quite extensively and therefore a great deal of effort to achieve little change – you can see the position as we left it in the third picture above.


Jean Claude will take on the next phase of construction which entails clearing all the floors in the south western part of the house, building a wall to replace the earth wall that has fallen down (see the post for 28 February 2007), forming the upstairs’ bedroom and en suite and the downstairs’ loo and putting in all the widows and doors. To that end we visited a builders’ merchant and bought 13 windows, two sets of external glazed double doors, eight internal doors, two wash hand-basins and two loos. Given the speed at which Jean Claude works we fully expect that there will be a functional bedroom with loo and wash hand-basin by the time we arrive in early April.

That last comment is based on the fact that we also have received a permit to dig up the road to install the septic tank. The contractor who is to do all the installation wishes to do the work immediately, and indeed is due to start on Monday 17 March, as the local authority is planning to resurface the road at the end of March. Which means that we will be able to let the local authority’s workmen do the top surfacing which will save some money and effort. Together with the sewerage pipe work we shall also put in pipe work to bring the electricity supply under the road and put in a pipe in case France Telecom also wishes to go underground. For this latter we visited their offices and it would appear that a connexion might be made above ground, but we are taking no chances in putting the pipe under the road.

So considerable progress this time and we feel very confident that we shall have a habitable house in time to face the rigours of winter.

Thursday, 7 February 2008

Quickening Pace





As planned we returned to Arne towards the end of January for a two week visit. After the pictures we had received from Jean Claude we were expecting great things and we were in no way disappointed. The pictures at the top of this post clearly demonstrate the great change that has been wrought to the roof. And what’s more given the good weather that has persisted in Arné over the past week it’s more than likely that the uncovered portion has now also been completed.

This leaves about a quarter of the roof still to be stripped out and replaced, but this is much the most difficult part of the job to be done. There are real problems with how to span such a large area, how to deal with the different levels between the house roof and that of the barn with which it interlocks and all of this affects, and is affected by, the issue of getting the heights for the ground and first floor right so that they ‘work’. Jean Claude is absolutely confident that he can sort all of this out and we have decided that we shall ‘go with the flow’ of the solutions that he works out – we’ll make the internal arrangements fit in with however the structure that emerges allows.

We also now have electricity on site. This was organised just as we were leaving last time and it was good to be able to disconnect from our very helpful neighbours and use our own supply. But it might not have been! For some reason EDF had a contact address for me in the next village and so letters that were sent to me demanding that I pay for the connexion costs did not reach me. It was only when we arrived back in Arné that I found out that EDF were proposing to cut off the supply over non-payment of their bill. The local EDF office only opens on Wednesdays between 9:00 and 11:45, so we went along at 11:00 to try to sort out the problems. To no avail though. We had been warned that EDF take an entirely capricious approach to business and are regularly uncontactable and this was the case. The gates were firmly locked and there was no one to be seen so we failed in this attempt. By this stage the letters from EDF were threatening a specific date on which to cut the supply. So I wrote a letter enclosing a cheque to cover the bill together with proper details of my address and sent it off hoping that this would stop the whole process. On the day appointed for disconnexion no one from EDF appeared and they haven’t done so since. But neither have I had any form of acknowledgement of my letter from EDF, I just have to hope that all is now well and that in due course we’ll be properly billed for future costs.

Progress has also occurred on the septic tank front. I have had a devis – a quote – from another local builder which is acceptable. Under instruction from him I went to the Mairie and completed the paperwork necessary to obtain permission to dig up the road that runs between our house and our field. This will allow for the outflow from the septic tank to go into a filter bed. The idea is that at the same time as the road is dug up for this purpose we’ll also get the electricity supply put under the road as well as a connexion to the nearest telecoms post. If we are fortunate all of this might just happen prior to our return on a more permanent basis in mid-April.

Finally we spent our time working around Jean Claude – we cleared away the rubbish he generated whilst taking the roof to pieces as well as clearing out areas of the house that need to be prepared for the re-arrangements of the internal space we plan. An awful lot of rotten wood came out of the house and we had a bonfire going permanently for almost all of the fortnight we were there. The result is that great changes have happened on the inside such that it will be possible to pour the concrete pretty soon to form ground the floor in about half of the house.

So, we are feeling much more confident that we shall indeed be able to go out to France in early April and stay there on a permanent basis. This is based on the expectation that we can create enough habitable space in the house prior to winter. Watch this space to see if this is entirely misplaced confidence!

Saturday, 29 December 2007

A Christmas Up-Date




We had not expected any need to post again until I returned to Arné in mid-January. However, we had an unexpected Christmas present in the form of an e-mail from our builder with several photos of the house attached; these are the ones posted above.

And you may understand our delight at receiving these as the progress made over the two weeks since we returned to the UK is very clearly visible. Virtually the whole of the western end of the house has now had the main structure of the roof rebuilt. The next step will be to put an impermeable membrane in place and then the laths on which the tiles will be laid. And then the tiles themselves can be laid – the new tiles have already been delivered to the house.

So at this rate of progress it would seem Jean Claude’s statement that this part of the roof will be complete by the time I make my January visit is likely to be fulfilled. And that will mean we have a dry area in which to start the next steps in the restoration.

Sunday, 16 December 2007

Now it all starts!




Having agreed to a quote and a start date with our French builder we decided to return to Arné to celebrate the commencement of the work on the house. All the stories indicated to us that we might well find that the promises to start would be broken. But quite the reverse has happened. We arrived to discover that the work had already commenced; part of the roof had had the tiles removed. And promptly on Monday as promised Jean Claude appeared and continued the process of removing the tiles – the broken ones are thrown away and those that are complete are stored for use back on the restored roof, which will give it an old look.

The next day having completed the work at the front we set to and took down all the trees that grew close to the back of the house. The most difficult was the very large pine that can be seen in the original photos of the house in the earliest postings. But Jean Claude was not daunted and he got it down and then cut it up into useful slices which we have stored to the side of the garden at the back. We also had a bonfire to get rid of all the useless spare wood. The difference made by all these changes can be seen in the photos at the top.

And then the process of stripping off the tiles proceeded at the back so that in the end there were no tiles at the western end of the house. The next step though was far more difficult; the problem of the wall that’s falling down reared its ugly head. With the removal of the roof the strength holding the wall up would be significantly reduced with the very real possibility that it would collapse. So, Jean Claude jammed three acrow props against the wall – see the picture above – and then also put strengthening concrete with iron reinforcement at two places across the crack, the pictures above show this.

And then the weather intervened – rain is a problem for roofing as it makes all movement across the roof extremely dangerous. We went for a visit to Biarritz where the weather proved to be beautiful. And when we returned we discovered that despite the rain Jean Claude had actually continued with his efforts on the roof stripping away the wood. A further day’s work has resulted in all the western end of the roof being removed so that there is effectively nothing left except the walls – as the pictures demonstrate. The next step was to create a reinforcing ring beam of concrete at the top of all the walls prior to the process of rebuilding the roof. Jean Claude was able to do this across most of the front of the house before the weather once again turned nasty with high winds and lashing rain. It was fortunate that he had managed this part of the work as he had stated to me that this area of wall was wobbly and could come down in a storm – the concrete reinforcement held throughout three days of abominable weather so we are confident that progress will continue without a collapse.

Jean Claude stated that if the weather holds sufficiently then he confidently expects that the roof for this part will be fully renovated by the middle/end of January and we shall be able to commence the internal works on this part to make it habitable enough for our use. We shall see!!

The other bit of progress has been the provision by EDF of a temporary electrical connexion on the post nearest to the house. Howard the electrician contacted EDF and despite the recent strikes managed to make the necessary arrangements. The next step which he will undertake is for a cable to be run from this temporary box to a board in the pigsties allowing equipment, and possibly the caravan, to be plugged in. We left before this could take place as the weather prevented any work on the electrics.

Notwithstanding this somewhat doubting comment about the timescale for the completion of the roof, it has been so encouraging to be here and witness the progress being made so rapidly. And when the weather has been so good as it has been, it has served only to reinforce our view that this will be the most wonderful place to have as our home.